Snohomish Logo
File #: 2023-0782    Version: 1
Type: Motion Status: Approved
File created: 6/28/2023 In control: General Legislative Session
On agenda: 7/19/2023 Final action: 7/19/2023
Title: Motion 23-289, authorizing the County Executive to sign Professional Services Agreement CCF04-23 with PH Consulting, LLC to provide design services for the 84th Street NE Corridor Spot Improvements Project
Attachments: 1. Motion 23-289, 2. Agreement - SIGNED, 3. Staff Report, 4. Action Plan, 5. Certificate of Insurance, 6. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 23-289, authorizing the County Executive to sign Professional Services Agreement CCF04-23 with PH Consulting, LLC to provide design services for the 84th Street NE Corridor Spot Improvements Project

body

DEPARTMENT:  Public Works

 

ORIGINATOR:  Lori Ericsson

 

EXECUTIVE RECOMMENDATION:  Approved by Ken Klein 6/30/23

 

PURPOSE: Approval of Agreement CCF04-23 will allow Snohomish County Public works to utilize PH Consulting, LLC to provide Design Services necessary to complete the 84th Street NE Corridor Spot Improvement project.

 

BACKGROUND: The Department of Public Works (PW) has received federal funding to complete spot safety improvements on the 84th Street NE Corridor from SR 9 to SR 92. 84th Street NE Corridor carries a high volume of traffic at high speeds which results in a high crash rate.  This project will design and implement the recommended near-term improvements as outlined in the 84th Street NE Corridor Implementation Action plan which is included in the ECAF package. The Transportation and Environmental Services division of PW does not currently have the staff capacity to complete Design Services for this project. Through a Request for Qualifications (RFQ) PW has solicited the services of a consultant to assist the County with this project.  PH Consulting, LLC responded to RFQ-23-002SB and was selected through established Federal, State and County policies and practices. This agreement includes technical reports, plans, estimates and specifications (PS&E) and environmental permitting. A Professional Services Agreement between Snohomish County and PH Consulting, LLC was negotiated.  The total budget for this ECAF is $104,842.54, which includes the agreement total amount of $95.311.40 and an additional 10% contingency amount of $9,531.14, for allowable unforeseen costs.  The approving motion for the agreement authorizes the Public Works Director or Deputy Director to approve and execute amendments to the agreement within this total budgeted amount.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

102 50610314109 Capital Consultant

$80,000.00

$15,311.40

$95,311.40

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$80,000.00

$15,311.40

$95,311.40

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

Road Fund 102

$80,000.00

$15,311.40

$95,311.40

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$80,000.00

$15,311.40

$95,311.40

 

DEPARTMENT FISCAL IMPACT NOTES:  This project is in the adopted 2023-2028 TIP under project no. D.67.03

 

CONTRACT INFORMATION:

ORIGINAL

X

CONTRACT#

CCF04-23

AMOUNT

$95,311.40

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL

START

Execution

END

6/30/2024

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by Risk - Shelia Barker 6/29/23 and Finance - Nathan Kennedy 6/29/23