Title: Motion 26-148, authorizing the County Executive to sign Phase 1 of the 2026-2028 Facilities On-Call Consultant Services Master Agreements under RFQ-25-0466RB
Attachments: 1. Proposed Motion 26-148, 2. Architect Agreement (ARC Architects), 3. Architect Agreement (KMD Architects), 4. Architect Agreement (WJA Design Collaborative), 5. Building Envelope Agreement (BEE Engineers), 6. Building Envelope Agreement (Walker Consultants), 7. Civil Engineering Agreement (Pace Engineers), 8. Civil Engineering Agreement (Reid Middleton), 9. Commissioning Agreement (Sazan Group), 10. Electrical Engineering Agreement (Sazan Group), 11. Electrical Engineering Agreement (Stantec Consulting), 12. Fire/Life Safety Agreement (Stantec Consulting), 13. Hazmat Testing Agreement (Terracon Consultants), 14. Hazmat Testing Agreement (WSP USA), 15. Material Testing Agreement (Certerra Northwest), 16. Material Testing Agreement (Otto Rosenau & Associates), 17. Material Testing Agreement (Terracon Consultants), 18. Roofing Agreement (Wetherholt & Associates), 19. Structural Engineering Agreement (CG Engineering), 20. Structural Engineering Agreement (PCS Structural Solutions), 21. Structural Engineering Agreement (Reid Middleton), 22. Survey Agreement (Harmsen), 23. Survey Agreement (Pace Engineers), 24. Insurance Approval, 25. Motion Assignment Slip
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 26-148, authorizing the County Executive to sign Phase 1 of the 2026-2028 Facilities On-Call Consultant Services Master Agreements under RFQ-25-0466RB

body

DEPARTMENT:  Facilities and Fleet Management

 

ORIGINATOR:  Anna Morton

 

EXECUTIVE RECOMMENDATION:  Approved by Tom Teigen 3/20/2026

 

PURPOSE: To authorize the County Executive to sign Phase 1 of the 2026-2028 Facilities On-Call Consultant Services Agreements under RFQ-25-0466RB.

 

BACKGROUND: The Facilities On-Call Consultant Services Program will be issuing multiple umbrella master agreements under a total of 11 disciplines. The terms of the agreements is 2 years from date of contract execution, with the option to extend or renew for up to two (2) additional one (1) year terms contingent upon budget appropriation. The execution of the Facilities On-Call Consultant Services Master Agreements would expedite the process of obtaining consultant services and move projects forward in an efficient manner. Work under each task assignment is performed under the direction of a Project Manager employed by the County. The specific scope and cost of each project will be negotiated under task assignments that will be authorized by the Executive or their designee. Total payments for services under the Master Agreements shall not exceed the umbrella amounts as outlined in Exhibit A. This request is to Expedite as the outgoing On-Call contracts expire April 5, 2026.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

Various Funds

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$15,750,000

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

  X

CONTRACT#

RFQ-25-0466RB

AMOUNT

$15,750,000

AMENDMENT

 

CONTRACT#

 

AMOUNT

 

 

Contract Period

ORIGINAL

START

4/6/2026

END

4/5/2028

AMENDMENT

START

 

END

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  One consultant is pending an insurance renewal before contract start date of April 6, 2026. See ECAF Notes.   Reviewed/approved by Risk Management (Stephanie Rousseau 3/18/2026) and Finance (Nathan Kennedy 3/20/2026)