File #: 2023-0982    Version: 1
Type: Motion Status: Approved
File created: 8/22/2023 In control: General Legislative Session
On agenda: 9/27/2023 Final action: 9/27/2023
Title: Motion 23-399, authorizing approval of Construction Change Order No. 9 for Meadowdale Beach Park and Estuary Restoration Project
Attachments: 1. Motion 23-399, 2. Change Order 9 - SIGNED, 3. Staff Report, 4. Memorandum, 5. Motion 23-211, 6. Motion 22-458, 7. Motion 22-347, 8. Motion 21-347, 9. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 23-399, authorizing approval of Construction Change Order No. 9 for Meadowdale Beach Park and Estuary Restoration Project

body

DEPARTMENT:  Conservation & Natural Resources

 

ORIGINATOR:  Rob Marchand

 

EXECUTIVE RECOMMENDATION:  Lacey Harper 9/12/23

 

PURPOSE: Approve Change Order No. 9

 

BACKGROUND: Change Order No. 9 in the amount of $1,073,872.06 ($971,829.92 plus 10.5% sales tax) incorporates work as described in Change Order Proposals: No. 20 for escalated construction costs incurred from the BNSF work stoppage in 2021, No. 21 for the addition of a retaining wall at the ADA entrance to the park, No. 23 for additional paving for the ADA road, and No. 24 for additional plants needed within the estuary. The County previously increased the contract time by 365 days in Change Order No. 7, so and extension of time is not required for this work.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

309-51094621326599 - REET2

1,073,872.06

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:    Funding available within current budget

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

PW-002-21SB

AMOUNT

$7,519,427.90

Change Order

1

CONTRACT#

PW-002-21SB

AMOUNT

   $125,752.08

Change Order

2

CONTRACT#

PW-002-21SB

AMOUNT

   $195,896.83

Change Order

3

CONTRACT#

PW-002-21SB

AMOUNT

     $53,159.61

Change Order

4

CONTRACT#

PW-002-21SB

AMOUNT

             $0.00

Change Order

5

CONTRACT#

PW-002-21SB

AMOUNT

  $312,887.82

Change Order

6

CONTRACT#

PW-002-21SB

AMOUNT

  $373,222.60

Change Order

7

CONTRACT#

PW-002-21SB

AMOUNT

             $0.00

Change Order

8

CONTRACT#

PW-002-21SB

AMOUNT

  $247,199.55

Change Order

9

CONTRACT#

PW-002-21SB

AMOUNT

$1,073,872.06

 

Contract Period

ORIGINAL

START

06/15/2021

END

07/20/2022

Change Order  4

START

7/21/2022

END

01/23/2023

Change Order  7

START

1/24/2023

END

04/03/2024

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Risk Management (Sheila Barker 8/23/23) and Finance (Nathan Kennedy 8/29/23)