Legislation Details

File #: 2026-2275    Version: 1
Type: Executive Status: Executive Approved
File created: 8/26/2026 In control: Executive
On agenda: Final action:
Title: Authorizing the County Executive to sign Change Order CO-33 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
Attachments: 1. PW-24-028SB Certificate of Insurance Renewed, 2. PW-24-028SB Agreement, 3. Motion 24-417, Amended, 4. PW24-028SB Tracking Log, 5. PW-24-028SB Change Order 01, 6. PW-24-028SB Change Order 02, 7. PW-24-028SB Change Order 03, 8. PW-24-028SB Change Order 04, 9. PW-24-028SB Change Order 05, 10. PW-24-028SB Change Order 06, 11. PW-24-028SB Change Order 07, 12. PW-24-028SB Change Order 08, 13. PW-24-028SB Change Order 09, 14. PW-24-028SB Change Order 10, 15. PW-24-028SB Change Order 11, 16. PW-24-028SB Change Order 12, 17. PW-24-028SB Change Order 13, 18. PW-24-028SB Change Order 14, 19. PW-24-028SB Change Order 15, 20. PW-24-028SB Change Order 16, 21. PW-24-028SB Change Order 17, 22. PW-24-028SB Change Order 18, 23. PW-24-028SB Change Order 19, 24. PW-24-028SB Change Order 20, 25. PW-24-028SB Change Order 21, 26. PW-24-028SB Change Order 22, 27. PW-24-028SB Change Order 23, 28. PW-24-028SB Change Order 24, 29. PW-24-028SB Change Order 25, 30. PW-24-028SB Change Order 26, 31. PW-24-028SB Change Order 27, 32. PW-24-028SB Change Order 28, 33. PW-24-028SB Change Order 29, 34. PW-24-028SB Change Order 30, 35. PW-24-028SB Change Order 31, 36. PW-24-028SB Change Order 32, 37. PW-24-028SB Change Order 33 - Proposed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Authorizing the County Executive to sign Change Order CO-33 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.

body

DEPARTMENT:  Facilities and Fleet

 

ORIGINATOR:  Lance Meinhold

 

EXECUTIVE RECOMMENDATION:  Approved

 

PURPOSE: To obtain Executive approval of Change Order 33 to Lincoln Construction, Inc.

 

BACKGROUND: The County and Lincoln Construction Inc. (LCi) entered into an agreement on December 19th, 2024, for the construction phase of the New Start Center of Edmonds. The Fire Marshal added several conditions to the work during final inspections. These items were not identified during plan reviews or previous inspections. This change order addresses those items related to the pedestrian gate. A window film has been added to the skylights in the multi-purpose room to reduce heat transfer. Collapsible, rubber transition strips have been added to the accessible showers after a request from the operator.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

002 5123116201

$9,369.00

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$9,369.00

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

PW24-028SB

AMOUNT

$2,474,000.00

AMENDMENT

1

CONTRACT#

PW24-028SB

AMOUNT

$547,000.00

AMENDMENT

2

CONTRACT#

PW24-028SB

AMOUNT

$128,884.00

AMENDMENT

3

CONTRACT#

PW24-028SB

AMOUNT

$-46,570.00

AMENDMENT

4

CONTRACT#

PW24-028SB

AMOUNT

$13,099.00

AMENDMENT

5

CONTRACT#

PW24-028SB

AMOUNT

$163,150.00

AMENDMENT

6

CONTRACT#

PW24-028SB

AMOUNT

$32,132.00

AMENDMENT

7

CONTRACT#

PW24-028SB

AMOUNT

$160,006.00

AMENDMENT

8

CONTRACT#

PW24-028SB

AMOUNT

$70,783.00

AMENDMENT

9

CONTRACT#

PW24-028SB

AMOUNT

$24,452.00

AMENDMENT

10

CONTRACT#

PW24-028SB

AMOUNT

$16,836.00

AMENDMENT

11

CONTRACT#

PW24-028SB

AMOUNT

$5,416.00

AMENDMENT

12

CONTRACT#

PW24-028SB

AMOUNT

$39,090.00

AMENDMENT

13

CONTRACT#

PW24-028SB

AMOUNT

$43,262.00

AMENDMENT

14

CONTRACT#

PW24-028SB

AMOUNT

$101,282.00

AMENDMENT

15

CONTRACT#

PW24-028SB

AMOUNT

$103,622.00

AMENDMENT

16

CONTRACT#

PW24-028SB

AMOUNT

$59,540.00

AMENDMENT

17

CONTRACT#

PW24-028SB

AMOUNT

$4,100.00

AMENDMENT

18

CONTRACT#

PW24-028SB

AMOUNT

$20,602.00

AMENDMENT

19

CONTRACT#

PW24-028SB

AMOUNT

$25,517.00

AMENDMENT

20

CONTRACT#

PW24-028SB

AMOUNT

$79,882.00

AMENDMENT

21

CONTRACT#

PW24-028SB

AMOUNT

$16,452.00

AMENDMENT

22

CONTRACT#

PW24-028SB

AMOUNT

$82,046.00

AMENDMENT

23

CONTRACT#

PW24-028SB

AMOUNT

$95,876.00

AMENDMENT

24

CONTRACT#

PW24-028SB

AMOUNT

$72,022.00

AMENDMENT

25

CONTRACT#

PW24-028SB

AMOUNT

$134,345.00

AMENDMENT

26

CONTRACT#

PW24-028SB

AMOUNT

$28,327.00

AMENDMENT

27

CONTRACT#

PW24-028SB

AMOUNT

$13,933.00

AMENDMENT

28

CONTRACT#

PW24-028SB

AMOUNT

$77,873.00

AMENDMENT

29

CONTRACT#

PW24-028SB

AMOUNT

$56,713.00

AMENDMENT

30

CONTRACT#

PW24-028SB

AMOUNT

$25,762.00

AMENDMENT

31

CONTRACT#

PW24-028SB

AMOUNT

$26,829.00

AMENDMENT

32

CONTRACT#

PW24-028SB

AMOUNT

$82,328.00

AMENDMENT

33

CONTRACT#

PW24-028SB

AMOUNT

$9,369.00

TOTAL

 

 

 

 

$4,787,960.00

 

Contract Period

ORIGINAL

START

12/19/2024

END

Final Project Acceptance Date

AMENDMENT

START

Upon Execution

END

Same - Unchanged

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Click or tap here to enter text.