Legislation Details
|
File #:
|
2026-0150
Version:
1
|
|
|
|
Type:
|
Executive
|
Status:
|
Executive Approved
|
|
Title:
|
Authorizing the County Executive to sign Change Order CO-25 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
|
|
Attachments:
|
1. PW-24-028SB Certificate of Insurance Renewed, 2. PW-24-028SB Agreement, 3. PW24-028SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-028SB Change Order 01, 6. PW-24-028SB Change Order 02, 7. PW-24-028SB Change Order 03, 8. PW-24-028SB Change Order 04, 9. PW-24-028SB Change Order 05, 10. PW-24-028SB Change Order 06, 11. PW-24-028SB Change Order 07, 12. PW-24-028SB Change Order 08, 13. PW-24-028SB Change Order 09, 14. PW-24-028SB Change Order 10, 15. PW-24-028SB Change Order 11, 16. PW-24-028SB Change Order 12, 17. PW-24-028SB Change Order 13, 18. PW-24-028SB Change Order 14, 19. PW-24-028SB Change Order 15, 20. PW-24-028SB Change Order 16, 21. PW-24-028SB Change Order 17, 22. PW-24-028SB Change Order 18, 23. PW-24-028SB Change Order 19, 24. PW-24-028SB Change Order 20, 25. PW-24-028SB Change Order 21, 26. PW-24-028SB Change Order 22, 27. PW-24-028SB Change Order 23, 28. PW-24-028SB Change Order 24, 29. PW-24-028SB Change Order 25 - Proposed, 30. PW-24-028SB Change Order 25 - EXEC SIGNED
|
Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the County Executive to sign Change Order CO-25 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
body
DEPARTMENT: Facilities and Fleet
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 25 to Lincoln Construction, Inc.
BACKGROUND: The County and Lincoln Construction Inc. (LCi) entered into an agreement on December 19th, 2024, for the construction phase of the New Start Center of Edmonds. Flooring preparation was more intense than had previously been expected. The existing drawings detailed out carpet in most of the residents’ rooms. Many had been switched to resilient flooring. Cleaning of the previous glue from the resilient flooring is more intensive than preparing an area previously covered in carpet. There was also significant damage from moisture below the existing finished floors which needed to be repaired prior to the new flooring being installed. The sub-contractor tracked their hours and materials for the work and reduced the cost by their previously assumed amounts. The City of Edmonds required additional fire stopping, fire caulking, and fire-resistant rated penetrations at many areas throughout the building. The drawings from the original construction were unclear about the intent of some of the existing construction assemblies. The change from transient residents to permanent residents (stay is greater than 30 days) triggers a higher level of protection for fire assemblies. The requests provide an additional layer of life safety protection compared to the previous conditions. Alternates suggested were both more costly and would have been more labor intensive, extending the project’s schedule. The sheet metal subcontractor has suggested replacing the wall caps around the entire building. Until now, the aim was to replace only the wall caps that had failed to date. The costs provided is very reasonable and should prevent failure of other locations around the building for years to come. The walls caps which failed created the majority of the wood rot found inside the building. The South County Fire Marshal requested additional fire lane striping upon plan approval, which did not occur until after Lincon was under contract. Room 315 did not have existing flooring, this was not noticed until after construction had started, it appears to have been the one room that incorrectly documented on the drawings.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
002 5123116201 |
$134,345.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$134,345.00 |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT# |
PW24-028SB |
AMOUNT |
$2,474,000.00 |
|
AMENDMENT |
1 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$547,000.00 |
|
AMENDMENT |
2 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$128,884.00 |
|
AMENDMENT |
3 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$-46,570.00 |
|
AMENDMENT |
4 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$13,099.00 |
|
AMENDMENT |
5 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$163,150.00 |
|
AMENDMENT |
6 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$32,132.00 |
|
AMENDMENT |
7 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$160,006.00 |
|
AMENDMENT |
8 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$70,783.00 |
|
AMENDMENT |
9 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$24,452.00 |
|
AMENDMENT |
10 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$16,836.00 |
|
AMENDMENT |
11 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$5,416.00 |
|
AMENDMENT |
12 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$39,090.00 |
|
AMENDMENT |
13 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$43,262.00 |
|
AMENDMENT |
14 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$101,282.00 |
|
AMENDMENT |
15 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$103,622.00 |
|
AMENDMENT |
16 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$59,540.00 |
|
AMENDMENT |
17 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$4,100.00 |
|
AMENDMENT |
18 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$20,602.00 |
|
AMENDMENT |
19 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$25,517.00 |
|
AMENDMENT |
20 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$79,882.00 |
|
AMENDMENT |
21 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$16,452.00 |
|
AMENDMENT |
22 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$82,046.00 |
|
AMENDMENT |
23 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$95,876.00 |
|
AMENDMENT |
24 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$72,022.00 |
|
AMENDMENT |
25 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$134,345.00 |
|
TOTAL |
|
|
|
|
$4,466,826.00 |
Contract Period
|
ORIGINAL |
START |
12/19/2024 |
END |
Final Project Acceptance Date |
|
AMENDMENT |
START |
Upon Execution |
END |
Same - Unchanged |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.
|