Snohomish Logo
File #: 2023-0026    Version: 1
Type: Motion Status: Approved
File created: 1/5/2023 In control: General Legislative Session
On agenda: 1/25/2023 Final action: 1/25/2023
Title: Motion 23-044, authorizing the County Executive to execute Amendment No. 7 to the Professional Services Agreement with J.A. Brennan Associates, PLLC for master plan update and day-use improvements at Kayak Point Park
Attachments: 1. Motion 23-044, 2. Staff Report, 3. Amendment 7 - SIGNED, 4. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 23-044, authorizing the County Executive to execute Amendment No. 7 to the Professional Services Agreement with J.A. Brennan Associates, PLLC for master plan update and day-use improvements at Kayak Point Park

body

DEPARTMENT:  Conservation & Natural Resources

 

ORIGINATOR:  Carol Ohlfs

 

EXECUTIVE RECOMMENDATION:  Lacey Harper (1/17/23)

 

PURPOSE: Approval for Professional Services Agreement Amendment No. 7 with J.A. Brennan Associates, PLLC for Kayak Point Park Day Use pier condition assessment

 

BACKGROUND: A consultant contract for professional services for Kayak Point Park was executed with J.A. Brennan Assoc. PLLC on Oct. 19, 2016 to update the Preferred Plan for the park and to also create a redevelopment concept for the day-use area of the facility.  The redevelopment concept was created to provide the basis for further design and ultimately the execution of the renovation.  This initial contract was followed by six subsequent amendments, the largest of which was to initiate detailed design for permitting and construction purposes, additional permit and design support and reporting requirements. This amendment will provide the next step in design services as included in the original RFP, to allow for construction support for Phase 1 construction.  Parks and J.A. Brennan Associates PLLC have negotiated an amendment for the value of $739,689 (Seven hundred thirty-nine thousand, six hundred eighty-nine dollars). This amount is available within current budget for the project.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

309-51094610326599

$739,689

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Funding available within current budget

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

Bid No. 024-15SB

AMOUNT

$554,999

AMENDMENT

1

CONTRACT#

 

AMOUNT

$16,835

AMENDMENT

2

CONTRACT#

 

AMOUNT

$24,717

AMENDMENT

3

CONTRACT#

 

AMOUNT

$1,721,577

AMENDMENT

4

CONTRACT#

 

AMOUNT

$43,158

AMENDMENT

5

CONTRACT#

 

AMOUNT

$144,674

AMENDMENT

6

CONTRACT#

 

AMOUNT

$12,618

AMENDMENT

7

CONTRACT#

 

AMOUNT

$739,689

 

Contract Period

ORIGINAL

START

NTP

END

12/31/2017

AMENDMENT

START

 

END

12/31/2025

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by Risk Management (Sheila Barker 1/9/23) and Finance (Nathan Kennedy 1/11/23)