Legislation Details

File #: 2026-2466    Version: 1
Type: Motion Status: Regular Agenda
File created: 9/23/2026 In control: Committee of the Whole
On agenda: 10/14/2026 Final action:
Title: Motion 26-400, approving Change Order No. 9 to the Arlington Operations Center Agreement with Cornerstone General Contractors
Attachments: 1. Proposed Motion 26-400, 2. Staff Report, 3. Change Order #9, 4. Progressive Design Build Contract Executed, 5. Amendment 1 Executed, 6. Amendment 2 Executed, 7. Amendment 3 Executed, 8. Amendment 4 Executed, 9. Amendment 5 Executed, 10. Certificate of Insurance, 11. Change Order #1 Executed, 12. Change Order #2 Executed, 13. Change Order #3 Executed, 14. Change Order #4 Executed, 15. Change Order #5 Executed, 16. Change Order #6 Executed, 17. Change Order #7 Executed, 18. Change Order #8 Executed, 19. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 26-400, approving Change Order No. 9 to the Arlington Operations Center Agreement with Cornerstone General Contractors

body

 

DEPARTMENT:  Public Works

 

ORIGINATOR:  Kelli Kunz

 

EXECUTIVE RECOMMENDATION:  Approved (Tom Teigen 10/1/2026)

 

PURPOSE: Approval of Change Order #9 to authorize payment to the Contractor, Cornerstone General Construction for added work associated Redesign of the EV Charging System

 

BACKGROUND: The Department of Public Works determined the need to construct a new road operations center and emergency response facility at the County’s Arlington Operations site located in Arlington, WA. • Through a Request for Qualifications and a subsequent Request for Proposal Public Works solicited the services of a Design Build Contractor or Consultant to assist the County with this project. Cornerstone General Contractors responded to RFQ-23-001SB and RFP-23-004SB and was selected through established Federal State and County policies and practices. • Snohomish County and Cornerstone General Construction entered into agreement on December 13, 2023, for the design and construction of the Arlington Operations Center under Progressive Design Build Agreement PDB01-23. • To date, PW has executed five amendments to the original agreement which include Validation (Motion No. 24-097), Design (Motion No. 24-317), Granite Falls Stating Site Construction (Motion No. 25-302) and Arlington Operations primary site construction (Motion No. 25-320). • This project was not bid but selected through an RFQ/RFP process and therefore requires Council approval for any contract amendments above $100,000 or 20% of the contract value, whichever is less. • To date there have been five amendments and six change orders approved by Council, and two change orders and one amendment approved by the PW Director. • An additional change order is needed above the PW Director’s authority and requires Council consideration: Change Order #9 Redesign of the EV Charging System. • The total request for change order 9 is $139,033.15, bringing the total contract amount NTE $31,953,403.56. • This project is fully bond funded and does not include any Road Fund dollars.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

306 501065016399 Construction

$139,033.15

 

$139,033.15

TOTAL

 

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

Fund 306 Arlington Operations Center

$139,033.15

 

$139,033.15

 

 

 

 

TOTAL

$139,033.15

 

$139,033.15

 

DEPARTMENT FISCAL IMPACT NOTES:  Funding for this project is included in the 2025-2026 Biennial budget.  This project is fully bond funded and does not include any work paid out of Road Fund dollars.  Work is expected to be completed in 2026.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

PDB01-23

AMOUNT

$0.00

AMENDMENT

1

CONTRACT#

PDB01-23

AMOUNT

$722,160.00

AMENDMENT

2

CONTRACT#

PDB01-23

AMOUNT

$3,192,544.00

AMENDMENT

3

CONTRACT#

PDB01-23

AMOUNT

$1,504,752.00

AMENDMENT

4

CONTRACT#

PDB01-23

AMOUNT

$25,215,490.00

AMENDMENT

5

CONTRACT#

PDB01-23

AMOUNT

$0.00

CHANGE ORDER

1

CONTRACT#

PDB01-23

AMOUNT

$27,319.16

CHANGE ORDER

2

CONTRACT#

PDB01-23

AMOUNT

$68,576.08

CHANGE ORDER

3

CONTRACT#

PDB01-23

AMOUNT

$41,960.01

CHANGE ORDER

4

CONTRACT#

PDB01-23

AMOUNT

$129,507.54

CHANGE ORDER

5

CONTRACT#

PDB01-23

AMOUNT

$57,004.68

CHANGE ORDER

6

CONTRACT#

PDB01-23

AMOUNT

$80,503.71

CHANGE ORDER

7

CONTRACT#

PDB01-23

AMOUNT

$4,979.47

CHANGE ORDER

8

CONTRACT#

PDB01-23

AMOUNT

$766,573.76

CHANGE ORDER

9

CONTRACT#

PDB01-23

AMOUNT

$139,033.15

 

Contract Period

ORIGINAL

START

12/13/23

END

Completion

AMENDMENT

START

2/29/24

END

Completion

AMENDMENT

START

8/21/24

END

Completion

AMENDMENT

START

7/10/25

END

Completion

AMENDMENT

START

7/17/25

END

Completion

AMENDMENT

START

4/30/26

END

Completion

CHANGE ORDER

START

3/11/26

END

Completion

CHANGE ORDER

START

3/11/26

END

Completion

CHANGE ORDER

START

4/28/26

END

Completion

CHANGE ORDER

START

4/28/26

END

Completion

CHANGE ORDER

START

4/28/26

END

Completion

CHANGE ORDER

START

6/4/26

END

Completion

CHANGE ORDER

START

7/22/26

END

Completion

CHANGE ORDER

START

8/27/26

END

Completion

CHANGE ORDER

START

Execution

END

Completion

 

 

 

 

 

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Risk Management (Tonya Woldrdige 9/30/2026) and Finance (Bill Thornton 10/1/2026).