Legislation Details
|
File #:
|
2026-1085
Version:
1
|
|
|
|
Type:
|
Executive
|
Status:
|
Executive Approved
|
|
File created:
|
4/25/2026
|
In control:
|
Executive
|
|
Title:
|
Authorizing the County Executive to sign Change Order CO-31 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
|
|
Attachments:
|
1. PW-24-028SB Agreement, 2. PW24-028SB Tracking Log, 3. Motion 24-417, Amended, 4. PW-24-028SB Change Order 01, 5. PW-24-028SB Change Order 02, 6. PW-24-028SB Change Order 03, 7. PW-24-028SB Change Order 04, 8. PW-24-028SB Change Order 05, 9. PW-24-028SB Change Order 06, 10. PW-24-028SB Change Order 07, 11. PW-24-028SB Change Order 08, 12. PW-24-028SB Change Order 09, 13. PW-24-028SB Change Order 10, 14. PW-24-028SB Change Order 11, 15. PW-24-028SB Change Order 12, 16. PW-24-028SB Change Order 13, 17. PW-24-028SB Change Order 14, 18. PW-24-028SB Change Order 15, 19. PW-24-028SB Change Order 16, 20. PW-24-028SB Change Order 17, 21. PW-24-028SB Change Order 18, 22. PW-24-028SB Change Order 19, 23. PW-24-028SB Change Order 20, 24. PW-24-028SB Change Order 21, 25. PW-24-028SB Change Order 22, 26. PW-24-028SB Change Order 23, 27. PW-24-028SB Change Order 24, 28. PW-24-028SB Change Order 25, 29. PW-24-028SB Change Order 26, 30. PW-24-028SB Change Order 27, 31. PW-24-028SB Change Order 28, 32. PW-24-028SB Change Order 29, 33. PW-24-028SB Change Order 30, 34. PW-24-028SB Change Order 31, 35. PW-24-028SB Certificate of Insurance Renewed
|
Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the County Executive to sign Change Order CO-31 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
body
DEPARTMENT: Facilities and Fleet
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approve.
PURPOSE: To obtain Executive approval of Change Order 31 to Lincoln Construction, Inc.
BACKGROUND: The County and Lincoln Construction Inc. (LCi) entered into an agreement on December 19th, 2024, for the construction phase of the New Start Center of Edmonds. The Fire Marshal is requiring additional gate controls. These items were not disclosed until the final fire inspection was requested.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
002 5123116201 |
$26,829.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$26,829.00 |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT# |
PW24-028SB |
AMOUNT |
$2,474,000.00 |
|
AMENDMENT |
1 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$547,000.00 |
|
AMENDMENT |
2 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$128,884.00 |
|
AMENDMENT |
3 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$-46,570.00 |
|
AMENDMENT |
4 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$13,099.00 |
|
AMENDMENT |
5 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$163,150.00 |
|
AMENDMENT |
6 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$32,132.00 |
|
AMENDMENT |
7 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$160,006.00 |
|
AMENDMENT |
8 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$70,783.00 |
|
AMENDMENT |
9 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$24,452.00 |
|
AMENDMENT |
10 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$16,836.00 |
|
AMENDMENT |
11 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$5,416.00 |
|
AMENDMENT |
12 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$39,090.00 |
|
AMENDMENT |
13 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$43,262.00 |
|
AMENDMENT |
14 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$101,282.00 |
|
AMENDMENT |
15 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$103,622.00 |
|
AMENDMENT |
16 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$59,540.00 |
|
AMENDMENT |
17 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$4,100.00 |
|
AMENDMENT |
18 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$20,602.00 |
|
AMENDMENT |
19 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$25,517.00 |
|
AMENDMENT |
20 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$79,882.00 |
|
AMENDMENT |
21 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$16,452.00 |
|
AMENDMENT |
22 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$82,046.00 |
|
AMENDMENT |
23 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$95,876.00 |
|
AMENDMENT |
24 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$72,022.00 |
|
AMENDMENT |
25 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$134,345.00 |
|
AMENDMENT |
26 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$28,327.00 |
|
AMENDMENT |
27 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$13,933.00 |
|
AMENDMENT |
28 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$77,873.00 |
|
AMENDMENT |
29 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$56,713.00 |
|
AMENDMENT |
30 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$25,762.00 |
|
AMENDMENT |
30 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$26,829.00 |
|
TOTAL |
|
|
|
|
$4,696,263.00 |
Contract Period
|
ORIGINAL |
START |
12/19/2024 |
END |
Final Project Acceptance Date |
|
AMENDMENT |
START |
Upon Execution |
END |
Same - Unchanged |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.
|