File #: 2025-3284    Version: 1
Type: Motion Status: Approved
File created: 10/6/2025 In control: General Legislative Session
On agenda: 10/15/2025 Final action: 10/15/2025
Title: Motion 25-476, authorizing the County Executive to sign Change Order CO-23 to Bid PW-24-027SB for the construction of the New Start Center of Everett with Marpac Construction
Attachments: 1. Motion 25-476, 2. Staff Report, 3. Change Order 23 - SIGNED, 4. Change Order 22, 5. Change Order 21, 6. Change Order 20, 7. Change Order 19, 8. Change Order 18, 9. Change Order 17, 10. Change Order 16, 11. Change Order 15, 12. Change Order 14, 13. Change Order 13, 14. Change Order 12, 15. Change Order 11, 16. Change Order 10, 17. Change Order 09, 18. Change Order 08, 19. Change Order 07, 20. Change Order 06, 21. Change Order 05, 22. Change Order 04, 23. Change Order 03, 24. Change Order 02, 25. Change Order 01, 26. Agreement, 27. Tracking Log, 28. Certificate of Insurance, 29. Reference Motion 24-417, Amended, 30. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 25-476, authorizing the County Executive to sign Change Order CO-23 to Bid PW-24-027SB for the construction of the New Start Center of Everett with Marpac Construction

body

DEPARTMENT:  Facilities and Fleet Management

 

ORIGINATOR:  Lance Meinhold

 

EXECUTIVE RECOMMENDATION:  Approved by Ken Klein 10/8/25

 

PURPOSE: To obtain Executive approval of Change Order 23 to Marpac Construction.

 

BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. Marpac Construction and the plumbing subcontractor, Streamline, air pressure tested the western third of the cold-water supply lines at the back building for one week. During the course of the week, they discovered the system is a combination of copper, galvanized steel, and plastic piping. The three plumbers repaired approximately 45 leaks. Marpac aided in uncovering areas and listening for leaks. Hearing air leaks in the system proved difficult due to the noise from Interstate 5 and the low pressure they were able to maintain. The system would need to hold 120 psi of air pressure in order to consider filling with water at 80 psi, normal operating pressure. By the end of the week, this portion of the system would not hold 10 psi of air pressure. This level of pressure could be achieved by friction along the length of the pipe. Basically, spending over 120 labor hours of work on 1/6 of the existing system resulted in no noticeable improvement. At this time, it is assumed the other 5/6 of the system will have similar issues. There is no way to know how many leaks will be found or how long repairs will take in make the system operable. Even if all of the current leaks are found and repaired, there is no way to guarantee a new leak will not develop within the first few weeks after placing the system back into operation. Newly developed leaks would be assumed to be inside asbestos bearing walls, requiring hazardous material abatement in addition to plumbing repairs. This change order is to provide a new system using PEX piping, the current economical, code compliant material for domestic water supplies. The change order provides the County with a warrantied system.  The asbestos containing materials around potential future water leaks would also have been mitigated. The change order provides a set timeline and cost for the completion of this scope of the work. The change order also includes impact costs to other scopes for items such as material storage for items which are due to arrive but cannot be installed until after the re-piping is complete. The construction plan is to complete the re-piping of the system in sections to allow other trades to restart working without requiring the complete system to be rebuilt first. The City of Everett Building Inspectors favor this approach. Marpac and the City are working with the County to allow occupancy of the front building prior to the completion of the back building. Marpac has calculated the schedule based on an approved Change Order by October 10th. Every day after October 10th and their receipt of an executed Change Order will result in an additional day being added to the schedule.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

002 5123116201

$683,833.00

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$683,833.00

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT #

PW 24-027SB

AMOUNT

$4,040,000.00

AMENDMENT

1

CONTRACT #

PW 24-027SB

AMOUNT

$12,354.58

AMENDMENT

2

CONTRACT #

PW 24-027SB

AMOUNT

$71,578.14

AMENDMENT

3

CONTRACT #

PW 24-027SB

AMOUNT

$7,040.92

AMENDMENT

4

CONTRACT #

PW 24-027SB

AMOUNT

$16,843.95

AMENDMENT

5

CONTRACT #

PW 24-027SB

AMOUNT

$200,329.05

AMENDMENT

6

CONTRACT #

PW 24-027SB

AMOUNT

$143,596.21

AMENDMENT

7

CONTRACT #

PW 24-027SB

AMOUNT

$106,047.50

AMENDMENT

8

CONTRACT #

PW 24-027SB

AMOUNT

$53,786.28

AMENDMENT

9

CONTRACT #

PW 24-027SB

AMOUNT

$123,892.39

AMENDMENT

10

CONTRACT #

PW 24-027SB

AMOUNT

$116,751.01

AMENDMENT

11

CONTRACT #

PW 24-027SB

AMOUNT

$126,919.65

AMENDMENT

12

CONTRACT #

PW 24-027SB

AMOUNT

$63,703.30

AMENDMENT

13

CONTRACT #

PW 24-027SB

AMOUNT

$87,029.01

AMENDMENT

14

CONTRACT #

PW 24-027SB

AMOUNT

$90,718.61

AMENDMENT

15

CONTRACT #

PW 24-027SB

AMOUNT

$86,707.91

AMENDMENT

16

CONTRACT #

PW 24-027SB

AMOUNT

$130,019.49

AMENDMENT

17

CONTRACT #

PW 24-027SB

AMOUNT

$55,849.00

AMENDMENT

18

CONTRACT #

PW 24-027SB

AMOUNT

$114,305.40

AMENDMENT

19

CONTRACT #

PW 24-027SB

AMOUNT

$63,031.00

AMENDMENT

20

CONTRACT #

PW 24-027SB

AMOUNT

$123,529.00

AMENDMENT

21

CONTRACT #

PW 24-027SB

AMOUNT

$72,777.00

AMENDMENT

22

CONTRACT #

PW 24-027SB

AMOUNT

$11,595.00

AMENDMENT

23

CONTRACT #

PW 24-027SB

AMOUNT

$683,833.00

 

 

 

 

TOTAL

$6,602,237.40

 

Contract Period

ORIGINAL

START

12/18/2024

END

Final Project Acceptance Date

AMENDMENT

START

Upon Execution

END

Same - Unchanged

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  (Risk Management (Sheila Barker 10/8/25) and Finance (Nathan Kennedy 10/8/25)