Legislation Details

File #: 2026-1995    Version: 1
Type: Motion Status: Approved
File created: 8/3/2026 In control: General Legislative Session
On agenda: 8/26/2026 Final action: 8/26/2026
Title: Motion 26-311, authorizing the Executive to approve Change Order No. 2 to Contract CA03-26 with Northwest Construction, Inc.
Attachments: 1. Motion 26-311, 2. Staff Report, 3. Change Order 2 - SIGNED, 4. Change Order 2 Justification, 5. Change Order 1, 6. Agreement, 7. Certificate of Insurance BNSF Railroad, 8. Certificate of Insurance NW Construction, 9. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 26-311, authorizing the Executive to approve Change Order No. 2 to Contract CA03-26 with Northwest Construction, Inc.

body

DEPARTMENT:  Public Works

 

ORIGINATOR:  Brian Larmore, P.E.

 

EXECUTIVE RECOMMENDATION:  Approved by Tom Teigen 8/6/26

 

PURPOSE: Approval of Change Order #2 to authorize payment to the contractor, Northwest Construction, for added work associated with adding drainage improvements and asphalt pavement to the container laydown area and existing access road.

 

BACKGROUND: Snohomish County and Northwest Construction entered into agreement #CA03-26 on May 7, 2026, for construction of the Intermodal Rail Yard Track Expansion Phase 1 project. • Adding drainage improvements and asphalt pavement to the container laydown area and existing access road improves and facilitates on-site waste operations during project construction. • This added work was programmed for construction in the subsequent Phase 2 project. • Adding this work now eliminates the need for future removal and reconstruction of temporary Phase 1 improvements. • These changes mitigate water quality regulatory risk during and after project construction. • Northwest Construction is entitled to additional compensation due to this added work. • The Intermodal Rail Yard Track Expansion Phase 1 project is located in Council District 2.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

402 50643756599

885,814.27

 

885,814.27

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

885,814.27

 

885,814.27

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

Solid Waste 402

885,814.27

 

885,814.27

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

885,814.27

 

885,814.27

 

DEPARTMENT FISCAL IMPACT NOTES:  Sufficient budget authority exists in the approved 2025-2026 budget. Project will be funded with Solid Waste Tip Fees.

 

CONTRACT INFORMATION:

ORIGINAL

X

CONTRACT#

CA03-26

AMOUNT

$5,241,604.67

CHANGE ORDER

1

CONTRACT#

CA03-26

AMOUNT

$(14,988.16)

CHANGE ORDER

2

CONTRACT#

CA03-26

AMOUNT

$ 885,814.27

 

Contract Period

ORIGINAL

START

05/07/2026

END

COMPLETION

CHANGE ORDER #1

START

07/23/2026

END

COMPLETION

CHANGE ORDER #2

START

UPON EXECUTION

END

COMPLETION

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Risk Management (Stephanie Rousseau 8/4/26) and Finance (Nathan Kennedy 8/5/26)