Executive/Council Action Form (ECAF)2025-0788
ITEM TITLE:
Title
Motion 25-142, authorizing the Snohomish County Executive to execute a contract for RFQ 24-011BC on-call sanitary sewer engineering with RH2 Engineering, Inc. at the Snohomish County Airport
body
DEPARTMENT: Airport
ORIGINATOR: Kevin Latschaw
EXECUTIVE RECOMMENDATION: Michael Fong 3/4/25
PURPOSE: To hire RH2 Engineering, Inc. for on-call Sanitary Sewer engineering services at Snohomish County Airport.
BACKGROUND:
• Snohomish County Airport (Paine Field) owns and operates its own sanitary sewer system and has a contract with Mukilteo Water and Wastewater District (MWWD) for wastewater disposal.
• Airport staff requires technical assistance with evaluating, maintaining and improving the airport’s sewer system.
• RH2 Engineering, Inc. has been selected on the basis of their qualifications to do the on-call Sanitary Sewer engineering work identified in Schedule E of RFQ 24-011BC.
• RH2 has extensive experience in sanitary sewer engineering, including providing various evaluations, plans, specifications and cost estimates for over 30 years at Paine Field.
• This contract will be administered over four years, with the ability to extend for additional time at the option of the County.
• The required funds will be provided from the Airport fund and supplemented with grant funding when available. The total expenditure shall not exceed $1,000,000.
• The Airport seeks authorization for the Executive to execute this professional services contract with RH2 Engineering, Inc.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
2025 |
2026-2027 |
TOTAL (3 years) |
410.521680.4101 - FAA Construction in Progress |
$200,000 |
$400,000 |
$600,000 |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$200,000 |
$400,000 |
$600,000 |
REVENUE: FUND, AGY, ORG, REV, SOURCE |
2025 |
2026-2027 |
TOTAL (3 years) |
410.621680.0800 - Fund Balance |
$200,000 |
$400,000 |
$600,000 |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$200,000 |
$400,000 |
$600,000 |
DEPARTMENT FISCAL IMPACT NOTES:
The airport shall only use this contract when funds are available and approved in the budget. In addition, the airport shall use FAA Grants or Passenger Facility Charges (PFC) whenever feasible.
CONTRACT INFORMATION:
ORIGINAL |
X |
CONTRACT# |
RFQ 24-011BC |
AMOUNT |
NTE$1,000,000 |
AMENDMENT |
|
CONTRACT# |
|
AMOUNT |
|
Contract Period
ORIGINAL X |
START |
03/01/2025 |
END |
12/31/2028 |
AMENDMENT |
START |
|
END |
|
OTHER DEPARTMENTAL REVIEW/COMMENTS: Reviewed/approved by: Risk Management (Sheila Barker 3/3/25), Finance (Nathan Kennedy 3/3/25), and Prosecuting Attorney’s Office as to form only (Michelle Corsi 2/26/25)