Title: Motion 21-459, authorizing the County Executive to execute Amendment No. 6 to the professional services agreement with J.A. Brennan Associates, PLLC for Master Plan Update and Day-Use Improvements At Kayak Point Park
Attachments: 1. Motion 21-459, 2. Staff Report, 3. Amendment No. 6 - SIGNED, 4. Motion Assignment Slip

Executive/Council Action Form (ECAF)

ITEM TITLE:

Title

Motion 21-459, authorizing the County Executive to execute Amendment No. 6 to the professional services agreement with J.A. Brennan Associates, PLLC for Master Plan Update and Day-Use Improvements At Kayak Point Park

body

DEPARTMENT:  Conservation & Natural Resources

 

ORIGINATOR:  Carol Ohlfs

 

EXECUTIVE RECOMMENDATION:  Approve-Lacey Harper 12/9/21

 

PURPOSE: Approval for Professional Services Agreement Amendment No. 6 with J.A. Brennan Associates, PLLC for Kayak Point Park Day Use pier condition assessment

 

BACKGROUND: A consultant contract for professional services for Kayak Point Park was executed with J.A. Brennan Assoc. PLLC on Oct. 19, 2016 to update the Preferred Plan for the park and to also create a redevelopment concept for the day-use area of the facility.  The redevelopment concept was created to provide the basis for further design and ultimately the execution of the renovation.  This initial contract was followed by five subsequent amendments, the largest of which was to initiate detailed design for permitting and construction purposes and a recent amendment for additional permit and design support. This amendment will provide required analysis of the structural condition of the pier after recent 2021 storm events, to identify additional damaged infrastructure.  Parks and J.A. Brennan Associates PLLC have negotiated an amendment for the value of $12,618 (Twelve thousand, six hundred eighteen dollars).  This amount is available within current budget for the project.

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

309-51094610326599 (KP REET 2)

$12,618

 

 

 

 

 

 

 

 

 

 

TOTAL

$12,618

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Funding available within current budget.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

Bid No. 024-15SB

AMOUNT

$554,999

AMENDMENT

1

CONTRACT#

 

AMOUNT

$16,835

AMENDMENT

2

CONTRACT#

 

AMOUNT

$24,717

AMENDMENT

3

CONTRACT#

 

AMOUNT

$1,721,577

AMENDMENT

4

CONTRACT#

 

AMOUNT

$43,158

AMENDMENT

5

CONTRACT#

 

AMOUNT

$144,674

AMENDMENT

6

CONTRACT#

 

AMOUNT

$12,618

 

Contract Period

ORIGINAL

START

NTP

END

12/31/2017

AMENDMENT

START

 

END

12/31/2025

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Approved as to form by DPA Sean Reay 12/3/21/Approved-Risk, Sheila Barker 12/8/21/Approved-Finance, Nathan Kennedy 12/8/21