Snohomish Logo
File #: 2024-1117    Version: 1
Type: Motion Status: Approved
File created: 5/23/2024 In control: General Legislative Session
On agenda: 6/26/2024 Final action: 6/26/2024
Title: Motion 24-237, authorizing the Snohomish County Executive to execute Change Order 2 to Contract PW23-004SB with Stacy and Witbeck, Inc. at the Snohomish County Airport
Sponsors: Airport, Nickolis Landgraff
Code sections: SCC 3.04.140 (4) - Amendments, change orders, and orders for extra work for $200,000 or less on contracts subject to bidding requirements for which sufficient appropriation authority exists may be awarded and approved by the county executive, except as provided in subsectio
Attachments: 1. Motion 24-237, 2. Staff Report, 3. Change Order 2 - SIGNED, 4. Change Order 1, 5. Contract, 6. Motion Assignment Slip

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Motion 24-237, authorizing the Snohomish County Executive to execute Change Order 2 to Contract PW23-004SB with Stacy and Witbeck, Inc. at the Snohomish County Airport

body

DEPARTMENT:  Airport

 

ORIGINATOR:  Kevin Latschaw

 

EXECUTIVE RECOMMENDATION:  A Boungjaktha

 

PURPOSE: To execute Change Order 2 to the construction contract with Stacy and Witbeck, Inc. to increase the compensation due to the contractor, and extend time for completion.

 

BACKGROUND: .

Q                     Snohomish County Airport awarded the Terminal Apron Reconstruction (advertisement PW-23-004SB, Motion 23-0288) to Stacy and Witbeck, Inc. (SWI) on 5/5/2023 for $9,344,639.69 inc. applicable sales tax.

Q                     In August 2023, SWI encountered a concrete-encased fiberoptic duct bank running under the terminal apron, at a much shallower depth than had been indicated in record drawings.  The duct bank carried most of the airport’s fiberoptic network, including the air traffic control tower and portions of the passenger terminal.

Q                     The actual location of the duct bank conflicted with the planned construction and required the removal and reconnection of all associated fiberoptics, in order to reinstall the duct bank at a greater depth. 

Q                     Change Order 2, in the amount of $791,181.05 (inc. sales tax) accounts for the cost of relocation, and associated costs due to the delay, as well as adds 34 calendar days to the contract duration.

Q                     The Airport seeks authorization for the Executive to execute this Change Order 2 with SWI in the amount of $791,181.05.

Q                     A prior Change Order 1 was executed on 3/15/2024, for $1,413.16 for various minor quantity adjustments.

Q                     Executing Change Order 2 would bring the new contract total to $10,137,233.90 (inc. sales tax).

Q                     The project is substantially complete as of November 2023, and no additional Change Orders are anticipated to complete the contract.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

410.521680.4101 - Professional Services

$791,181.05

 

$791,181.05

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$791,181.05

 

$791,181.05

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

410.621680.0800 - Fund Balance

$791,181.05

 

$791,181.05

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$791,181.05

 

$791,181.05

 

DEPARTMENT FISCAL IMPACT NOTES:  This project is funded from the Airport Departments fund balance but shall be reimbursed by bonds issued under our Passenger Facility Charge (PFC) Program. The PFC Program bonds shall be repaid using future PFC revenue collected from terminal passengers at $4.50 per enplaned passenger.  PFC bonds shall be issued up to $9M and the remaining is reimbursed via the “pay as you go” program of instant reimbursement from PFC collections. 

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT#

PW-23-004SB

AMOUNT

$9,344,639.69

AMENDMENT

 

CONTRACT#

PW-23-004SB

AMOUNT

$1,413.16

AMENDMENT

X

CONTRACT#

PW-23-004SB

AMOUNT

$791,181.05

 

Contract Period

ORIGINAL

START

7/6/2023

END

10/10/2023

AMENDMENT

START

7/6/2023

END

10/10/2023

AMENDMENT

START

7/6/2023

END

11/15/2023

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Reviewed/approved by:  Risk Management (Sheila Barker 5/24/24) and Finance (Brian Haseleu 5/28/24)