Title:
|
Authorizing the Executive to sign Change Order CO-34 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
|
|
Attachments:
|
1. PW-24-027SB Certificate of Insurance, 2. PW24-027SB Tracking Log, 3. PW-24-027SB Agreement, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 05, 10. PW-24-027SB Change Order 06, 11. PW-24-027SB Change Order 07, 12. PW-24-027SB Change Order 08, 13. PW-24-027SB Change Order 09, 14. PW-24-027SB Change Order 10, 15. PW-24-027SB Change Order 11, 16. PW-24-027SB Change Order 12, 17. PW-24-027SB Change Order 13, 18. PW-24-027SB Change Order 14, 19. PW-24-027SB Change Order 15, 20. PW-24-027SB Change Order 16, 21. PW-24-027SB Change Order 17, 22. PW-24-027SB Change Order 18, 23. PW-24-027SB Change Order 19, 24. PW-24-027SB Change Order 20, 25. PW-24-027SB Change Order 21, 26. PW-24-027SB Change Order 22, 27. PW-24-027SB Change Order 23, 28. PW-24-027SB Change Order 24, 29. PW-24-027SB Change Order 25, 30. PW-24-027SB Change Order 26, 31. PW-24-027SB Change Order 27, 32. PW-24-027SB Change Order 28, 33. PW-24-027SB Change Order 29, 34. PW-24-027SB Change Order 30 - ECAF 2026-0224, 35. PW-24-027SB Change Order 31 - ECAF 2026-0293, 36. PW-24-027SB Change Order 32 - ECAF 2026-0311, 37. PW-24-027SB Change Order 33 - ECAF 2026-0332, 38. PW-24-027SB Change Order - Proposed
|
Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the Executive to sign Change Order CO-34 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
body
DEPARTMENT: Facilities and Fleet Management
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 34 to Marpac Construction.
BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The exterior guard rails at Building B were only attached to the decorative column covers and with undersized bolts to the deck slab at the mid-point of the runs. During the course of exploratory demolition of the trim at the walkway, eleven of the columns at the exterior walkway were discovered to lack any positive attachment to the walkway deck. The columns have been replaced by using the bid allowance funds. However, those funds have now been exhausted. After the removal of the trim, the guard rails along the entire length of the walkway at Building B are no longer stable and must be replaced. The design, engineering, and construction teams accessed several options for the replacement railing. The selected system was the most cost effective. Additionally, the work at the railing can only safely be completed after work in the adjacent rooms both above and below are complete. Thus, ten days are being added to the project schedule to safely coordinate the replacement of the railing.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
002 5123116201 |
$148,440.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$148,440.00 |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT # |
PW 24-027SB |
AMOUNT |
$4,040,000.00 |
|
AMENDMENT |
1 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$12,354.58 |
|
AMENDMENT |
2 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$71,578.14 |
|
AMENDMENT |
3 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$7,040.92 |
|
AMENDMENT |
4 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$16,843.95 |
|
AMENDMENT |
5 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$200,329.05 |
|
AMENDMENT |
6 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$143,596.21 |
|
AMENDMENT |
7 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$106,047.50 |
|
AMENDMENT |
8 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$53,786.28 |
|
AMENDMENT |
9 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$123,892.39 |
|
AMENDMENT |
10 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$116,751.01 |
|
AMENDMENT |
11 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$126,919.65 |
|
AMENDMENT |
12 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$63,703.30 |
|
AMENDMENT |
13 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$87,029.01 |
|
AMENDMENT |
14 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$90,718.61 |
|
AMENDMENT |
15 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$86,707.91 |
|
AMENDMENT |
16 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$130,019.49 |
|
AMENDMENT |
17 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$55,849.00 |
|
AMENDMENT |
18 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$114,305.40 |
|
AMENDMENT |
19 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$63,031.00 |
|
AMENDMENT |
20 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$123,529.00 |
|
AMENDMENT |
21 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$72,777.00 |
|
AMENDMENT |
22 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$11,595.00 |
|
AMENDMENT |
23 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$683,833.00 |
|
AMENDMENT |
24 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$55,593.00 |
|
AMENDMENT |
25 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$37,182.00 |
|
AMENDMENT |
26 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$12,244.00 |
|
AMENDMENT |
27 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$45,111.00 |
|
AMENDMENT |
28 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$46,191.00 |
|
AMENDMENT |
29 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$72.00 |
|
AMENDMENT |
30 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$25,316.00 |
|
AMENDMENT |
31 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$106,683.00 |
|
AMENDMENT |
32 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$89,575.00 |
|
AMENDMENT |
33 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$68,858.00 |
|
AMENDMENT |
34 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$148,440 |
|
|
|
|
|
TOTAL |
$7,237,502.40 |
Contract Period
|
ORIGINAL |
START |
12/18/2024 |
END |
Final Project Acceptance Date |
|
AMENDMENT |
START |
Upon Execution |
END |
Same - Unchanged |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.
|