Legislation Details

File #: 2026-0349    Version: 1
Type: Executive Status: Executive Approved
File created: 1/30/2026 In control: Executive
On agenda: Final action:
Title: Authorizing the Executive to sign Change Order CO-34 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
Attachments: 1. PW-24-027SB Certificate of Insurance, 2. PW24-027SB Tracking Log, 3. PW-24-027SB Agreement, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 05, 10. PW-24-027SB Change Order 06, 11. PW-24-027SB Change Order 07, 12. PW-24-027SB Change Order 08, 13. PW-24-027SB Change Order 09, 14. PW-24-027SB Change Order 10, 15. PW-24-027SB Change Order 11, 16. PW-24-027SB Change Order 12, 17. PW-24-027SB Change Order 13, 18. PW-24-027SB Change Order 14, 19. PW-24-027SB Change Order 15, 20. PW-24-027SB Change Order 16, 21. PW-24-027SB Change Order 17, 22. PW-24-027SB Change Order 18, 23. PW-24-027SB Change Order 19, 24. PW-24-027SB Change Order 20, 25. PW-24-027SB Change Order 21, 26. PW-24-027SB Change Order 22, 27. PW-24-027SB Change Order 23, 28. PW-24-027SB Change Order 24, 29. PW-24-027SB Change Order 25, 30. PW-24-027SB Change Order 26, 31. PW-24-027SB Change Order 27, 32. PW-24-027SB Change Order 28, 33. PW-24-027SB Change Order 29, 34. PW-24-027SB Change Order 30 - ECAF 2026-0224, 35. PW-24-027SB Change Order 31 - ECAF 2026-0293, 36. PW-24-027SB Change Order 32 - ECAF 2026-0311, 37. PW-24-027SB Change Order 33 - ECAF 2026-0332, 38. PW-24-027SB Change Order - Proposed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Authorizing the Executive to sign Change Order CO-34 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.

body

DEPARTMENT:  Facilities and Fleet Management

 

ORIGINATOR:  Lance Meinhold

 

EXECUTIVE RECOMMENDATION:  Approved

 

PURPOSE: To obtain Executive approval of Change Order 34 to Marpac Construction.

 

BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The exterior guard rails at Building B were only attached to the decorative column covers and with undersized bolts to the deck slab at the mid-point of the runs. During the course of exploratory demolition of the trim at the walkway, eleven of the columns at the exterior walkway were discovered to lack any positive attachment to the walkway deck. The columns have been replaced by using the bid allowance funds. However, those funds have now been exhausted. After the removal of the trim, the guard rails along the entire length of the walkway at Building B are no longer stable and must be replaced. The design, engineering, and construction teams accessed several options for the replacement railing. The selected system was the most cost effective. Additionally, the work at the railing can only safely be completed after work in the adjacent rooms both above and below are complete. Thus, ten days are being added to the project schedule to safely coordinate the replacement of the railing.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

002 5123116201

$148,440.00

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$148,440.00

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT #

PW 24-027SB

AMOUNT

$4,040,000.00

AMENDMENT

1

CONTRACT #

PW 24-027SB

AMOUNT

$12,354.58

AMENDMENT

2

CONTRACT #

PW 24-027SB

AMOUNT

$71,578.14

AMENDMENT

3

CONTRACT #

PW 24-027SB

AMOUNT

$7,040.92

AMENDMENT

4

CONTRACT #

PW 24-027SB

AMOUNT

$16,843.95

AMENDMENT

5

CONTRACT #

PW 24-027SB

AMOUNT

$200,329.05

AMENDMENT

6

CONTRACT #

PW 24-027SB

AMOUNT

$143,596.21

AMENDMENT

7

CONTRACT #

PW 24-027SB

AMOUNT

$106,047.50

AMENDMENT

8

CONTRACT #

PW 24-027SB

AMOUNT

$53,786.28

AMENDMENT

9

CONTRACT #

PW 24-027SB

AMOUNT

$123,892.39

AMENDMENT

10

CONTRACT #

PW 24-027SB

AMOUNT

$116,751.01

AMENDMENT

11

CONTRACT #

PW 24-027SB

AMOUNT

$126,919.65

AMENDMENT

12

CONTRACT #

PW 24-027SB

AMOUNT

$63,703.30

AMENDMENT

13

CONTRACT #

PW 24-027SB

AMOUNT

$87,029.01

AMENDMENT

14

CONTRACT #

PW 24-027SB

AMOUNT

$90,718.61

AMENDMENT

15

CONTRACT #

PW 24-027SB

AMOUNT

$86,707.91

AMENDMENT

16

CONTRACT #

PW 24-027SB

AMOUNT

$130,019.49

AMENDMENT

17

CONTRACT #

PW 24-027SB

AMOUNT

$55,849.00

AMENDMENT

18

CONTRACT #

PW 24-027SB

AMOUNT

$114,305.40

AMENDMENT

19

CONTRACT #

PW 24-027SB

AMOUNT

$63,031.00

AMENDMENT

20

CONTRACT #

PW 24-027SB

AMOUNT

$123,529.00

AMENDMENT

21

CONTRACT #

PW 24-027SB

AMOUNT

$72,777.00

AMENDMENT

22

CONTRACT #

PW 24-027SB

AMOUNT

$11,595.00

AMENDMENT

23

CONTRACT #

PW 24-027SB

AMOUNT

$683,833.00

AMENDMENT

24

CONTRACT #

PW 24-027SB

AMOUNT

$55,593.00

AMENDMENT

25

CONTRACT #

PW 24-027SB

AMOUNT

$37,182.00

AMENDMENT

26

CONTRACT #

PW 24-027SB

AMOUNT

$12,244.00

AMENDMENT

27

CONTRACT #

PW 24-027SB

AMOUNT

$45,111.00

AMENDMENT

28

CONTRACT #

PW 24-027SB

AMOUNT

$46,191.00

AMENDMENT

29

CONTRACT #

PW 24-027SB

AMOUNT

$72.00

AMENDMENT

30

CONTRACT #

PW 24-027SB

AMOUNT

$25,316.00

AMENDMENT

31

CONTRACT #

PW 24-027SB

AMOUNT

$106,683.00

AMENDMENT

32

CONTRACT #

PW 24-027SB

AMOUNT

$89,575.00

AMENDMENT

33

CONTRACT #

PW 24-027SB

AMOUNT

$68,858.00

AMENDMENT

34

CONTRACT #

PW 24-027SB

AMOUNT

$148,440

 

 

 

 

TOTAL

$7,237,502.40

 

Contract Period

ORIGINAL

START

12/18/2024

END

Final Project Acceptance Date

AMENDMENT

START

Upon Execution

END

Same - Unchanged

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Click or tap here to enter text.