|
Legislation Details
|
File #:
|
2025-2552
Version:
1
|
|
|
|
Type:
|
Executive
|
Status:
|
Executive Approved
|
|
Title:
|
Authorizing the Executive to sign of Change Order CO-14 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
|
|
Attachments:
|
1. PW-24-027SB Certificate of Insurance, 2. PW-24-027SB Agreement, 3. PW24-027SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 05, 10. PW-24-027SB Change Order 06, 11. PW-24-027SB Change Order 07, 12. PW-24-027SB Change Order 08, 13. PW-24-027SB Change Order 09, 14. PW-24-027SB Change Order 10, 15. PW-24-027SB Change Order 11, 16. PW-24-027SB Change Order 12, 17. PW-24-027SB Change Order 13 - ECAF 2025-2546, 18. PW-24-027SB Change Order 14 - Proposed, 19. PW-24-027SB Change Order 14 - Exec Signed
|
Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the Executive to sign of Change Order CO-14 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
body
DEPARTMENT: Facilities and Fleet Management
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The contractor has suggested an alternative method for routing fire protection piping and fire alarm wiring through the back building. The design intent during the bid was to route the utilities through the attic space and then down, through wall cavities to each individual room. Asbestos containing materials have been found in the wall cavities and attic areas. Those materials would need to be abated in order to complete the work per the bid documents. Heat trace wire would have been required to protect all of the piping within the attic space, as the space is not heated but is insulated from the occupied space. Structural upgrades for supporting the piping within the attic space would also have been required. These requirements were not known at the time of the bid. Following the bid documents would have produced a change order of approximately $160,000. The savings to the project by using this alternate methodology is approximately $70,000.
BACKGROUND: Click or tap here to enter text.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
124 509 044 66 6201 |
$90,718.61 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$90,718.61 |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT # |
PW 24-027SB |
AMOUNT |
$4,040,000.00 |
|
AMENDMENT |
1 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$12,354.58 |
|
AMENDMENT |
2 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$71,578.14 |
|
AMENDMENT |
3 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$7,040.92 |
|
AMENDMENT |
4 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$16,843.95 |
|
AMENDMENT |
5 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$200,329.05 |
|
AMENDMENT |
6 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$143,596.21 |
|
AMENDMENT |
7 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$106,047.50 |
|
AMENDMENT |
8 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$53,786.28 |
|
AMENDMENT |
9 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$123,892.39 |
|
AMENDMENT |
10 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$116,751.01 |
|
AMENDMENT |
11 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$126,919.65 |
|
AMENDMENT |
12 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$63,703.30 |
|
AMENDMENT |
13 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$87,029.01 |
|
AMENDMENT |
14 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$90,718.61 |
|
|
|
|
|
TOTAL |
$5,260,590.60 |
Contract Period
|
ORIGINAL |
START |
12/18/2024 |
END |
Final Project Acceptance Date |
|
AMENDMENT |
START |
Upon Execution |
END |
Same - Unchanged |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.
|