Motion 25-338, authorizing the Executive to approve Change Order No. 12 to Contract CA04-24 with Marshbank Construction, Inc.
|
Attachments:
|
1. Proposed Motion 25-338, 2. Staff Report, 3. Change Order 12, 4. Change Order 11, 5. Change Order 10, 6. Change Order 9, 7. Change Order 8, 8. Change Order 7, 9. Change Order 6, 10. Change Order 5, 11. Change Order 4, 12. Change Order 3, 13. Change Order 2, 14. Change Order 1, 15. Agreement, 16. Motion Assignment Slip
|
Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Motion 25-338, authorizing the Executive to approve Change Order No. 12 to Contract CA04-24 with Marshbank Construction, Inc.
body
DEPARTMENT: Public Works
ORIGINATOR: Brian Larmore, P.E.
EXECUTIVE RECOMMENDATION: Approved by Ken Klein 7/15/25
PURPOSE: To approve Change Order #12 to authorize payment to the Contractor, Marshbank Construction Inc. for added work associated with the disposal of existing soils that were found to contain petroleum products.
BACKGROUND: Snohomish County and Marshbank Construction entered into agreement #CA04-24 on March 29, 2024, for construction of the 36th Ave W & 35th Ave W, 164th ST SW to SR99 Improvement Project The project unexpectedly encountered the presence of Class II petroleum-based materials in the existing roadway subgrade and soils. Removal and disposal of these Class II materials is required to construct the roadway improvements. The project is limited in the disposal of these materials and disposal cost is higher that disposal of clean soils. Marshbank Construction is entitled to renegotiate compensation due to this unforeseen condition. The 35th/36th project is in Council District 3.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
102 50630336399 Contractor Payments |
$344,250.00 |
|
$344,250.00 |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$344,250.00 |
|
$344,250.00 |
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
Road Fund 102 |
$344,250.00 |
|
$344,250.00 |
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$344,250.00 |
|
$344,250.00 |
DEPARTMENT FISCAL IMPACT NOTES: RC1783 & RC1784, E.40.02 & E.40.03 in the 2025 ACP
CONTRACT INFORMATION:
ORIGINAL |
|
CONTRACT# |
CA04-24 |
AMOUNT |
$9,890,354.21 |
AMENDMENT |
1 |
CONTRACT# |
CA04-24 |
AMOUNT |
$316,750.00 |
AMENDMENT |
2 |
CONTRACT# |
CA04-24 |
AMOUNT |
$-57,216.00 |
AMENDMENT |
3 |
CONTRACT# |
CA04-24 |
AMOUNT |
$249,149.88 |
AMENDMENT |
4 |
CONTRACT# |
CA04-24 |
AMOUNT |
$2,354.76 |
AMENDMENT |
5 |
CONTRACT# |
CA04-24 |
AMOUNT |
$123,511.38 |
AMENDMENT |
6 |
CONTRACT# |
CA04-24 |
AMOUNT |
$73,773.12 |
AMENDMENT |
7 |
CONTRACT# |
CA04-24 |
AMOUNT |
$18,266.32 |
AMENDMENT |
8 |
CONTRACT# |
CA04-24 |
AMOUNT |
$12,300.00 |
AMENDMENT |
9 |
CONTRACT# |
CA04-24 |
AMOUNT |
$20,410.00 |
AMENDMENT |
10 |
CONTRACT# |
CA04-24 |
AMOUNT |
$321,348.54 |
AMENDMENT |
11 |
CONTRACT# |
CA04-24 |
AMOUNT |
$405,408.30 |
AMENDMENT |
12 |
CONTRACT# |
CA04-24 |
AMOUNT |
$344,250.00 |
Contract Period
ORIGINAL |
START |
03/29/2024 |
END |
At Completion |
AMENDMENT 1 |
START |
08/29/2024 |
END |
At Completion |
AMENDMENT 2 |
START |
09/11/2024 |
END |
At Completion |
AMENDMENT 3 |
START |
10/16/2024 |
END |
At Completion |
AMENDMENT 4 |
START |
12/05/2024 |
END |
At Completion |
AMENDMENT 5 |
START |
12/30/2024 |
END |
At Completion |
AMENDMENT 6 |
START |
12/30/2024 |
END |
At Completion |
AMENDMENT 7 |
START |
01/06/2025 |
END |
At Completion |
AMENDMENT 8 |
START |
01/30/2025 |
END |
At Completion |
AMENDMENT 9 |
START |
03/07/2025 |
END |
At Completion |
AMENDMENT 10 |
START |
04/14/2025 |
END |
At Completion |
AMENDMENT 11 |
START |
05/09/2025 |
END |
At Completion |
AMENDMENT 12 |
START |
Pending |
END |
At Completion |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Reviewed/approved by: Risk Management (Sheila Barker 7/9/25) and Finance (Nathan Kennedy 7/11/25)
|