Legislation Details
|
File #:
|
2025-3905
Version:
1
|
|
|
|
Type:
|
Executive
|
Status:
|
Executive Approved
|
|
File created:
|
12/18/2025
|
In control:
|
Executive
|
|
Title:
|
Authorizing the County Executive to sign Change Order CO-24 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
|
|
Attachments:
|
1. PW-24-028SB Certificate of Insurance Renewed, 2. PW-24-028SB Agreement, 3. PW24-028SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-028SB Change Order 01, 6. PW-24-028SB Change Order 02, 7. PW-24-028SB Change Order 03, 8. PW-24-028SB Change Order 04, 9. PW-24-028SB Change Order 05, 10. PW-24-028SB Change Order 06, 11. PW-24-028SB Change Order 07, 12. PW-24-028SB Change Order 08, 13. PW-24-028SB Change Order 09, 14. PW-24-028SB Change Order 10, 15. PW-24-028SB Change Order 11, 16. PW-24-028SB Change Order 12, 17. PW-24-028SB Change Order 13, 18. PW-24-028SB Change Order 14, 19. PW-24-028SB Change Order 15, 20. PW-24-028SB Change Order 16, 21. PW-24-028SB Change Order 17, 22. PW-24-028SB Change Order 18, 23. PW-24-028SB Change Order 19, 24. PW-24-028SB Change Order 20, 25. PW-24-028SB Change Order 21, 26. PW-24-028SB Change Order 22 - ECAF 2025-3881, 27. PW-24-028SB Change Order 23 - ECAF 2025-3904, 28. PW-24-028SB Change Order 24 - Proposed, 29. PW-24-028SB Change Order 24 - Exec Signed
|
Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the County Executive to sign Change Order CO-24 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
body
DEPARTMENT: Facilities and Fleet
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 24 to Lincoln Construction, Inc.
BACKGROUND: The County and Lincoln Construction Inc. (LCi) entered into an agreement on December 19th, 2024, for the construction phase of the New Start Center of Edmonds. The City of Edmonds required the improvements to include Electrical Vehicle charging stations for 15 devices ready to use without future updates to the electrical system of the building. The existing service to the building is sufficient for the current uses; however, the existing services would not be able to support the future EV charging stations. Thus, the electrical services to the building must be increased. This Change Order allows for the Contractor to provide the portions of the electrical upgrades which are not installed by SnoPUD. The construction costs from SnoPUD are a separate issue.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
002 5123116201 |
$72,022.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$72,022.00 |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT# |
PW24-028SB |
AMOUNT |
$2,474,000.00 |
|
AMENDMENT |
1 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$547,000.00 |
|
AMENDMENT |
2 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$128,884.00 |
|
AMENDMENT |
3 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$-46,570.00 |
|
AMENDMENT |
4 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$13,099.00 |
|
AMENDMENT |
5 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$163,150.00 |
|
AMENDMENT |
6 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$32,132.00 |
|
AMENDMENT |
7 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$160,006.00 |
|
AMENDMENT |
8 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$70,783.00 |
|
AMENDMENT |
9 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$24,452.00 |
|
AMENDMENT |
10 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$16,836.00 |
|
AMENDMENT |
11 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$5,416.00 |
|
AMENDMENT |
12 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$39,090.00 |
|
AMENDMENT |
13 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$43,262.00 |
|
AMENDMENT |
14 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$101,282.00 |
|
AMENDMENT |
15 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$103,622.00 |
|
AMENDMENT |
16 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$59,540.00 |
|
AMENDMENT |
17 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$4,100.00 |
|
AMENDMENT |
18 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$20,602.00 |
|
AMENDMENT |
19 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$25,517.00 |
|
AMENDMENT |
20 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$79,882.00 |
|
AMENDMENT |
21 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$16,452.00 |
|
AMENDMENT |
22 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$82,046.00 |
|
AMENDMENT |
23 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$95,876.00 |
|
AMENDMENT |
24 |
CONTRACT# |
PW24-028SB |
AMOUNT |
$72,022.00 |
|
TOTAL |
|
|
|
|
$4,332,481.00 |
Contract Period
|
ORIGINAL |
START |
12/19/2024 |
END |
Final Project Acceptance Date |
|
AMENDMENT |
START |
Upon Execution |
END |
Same - Unchanged |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.
|