Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Interagency Agreement with WAEVCP for Vehicle Depot Charging for 3 County Sites
body
DEPARTMENT: Facilities and Fleet
ORIGINATOR: Al Garcia
EXECUTIVE RECOMMENDATION: Click or tap here to enter text.
PURPOSE: Executive’s Approval of Interagency Agreement with the Washington Electric Vehicle Charging Program (WAEVCP) to install 60 L2 Ports at 3 Snohomish County sites
BACKGROUND: WAEVCP is awarding the County a $509,000 grant to match a $400,000 county investment to install 60 L2 Ports at 3 Snohomish County locations for a total project cost of $909.000. Motion 24-128, passed by Council on March 19, 2024, gave the County Executive the authority to sign contracts relating to funds awarded by WAEVCP on this project.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
502 5188606000 Capital Cost |
$509,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$509,000 |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
502 3188606991 Other Rev/Grans |
$509,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$509,000 |
|
|
DEPARTMENT FISCAL IMPACT NOTES: Supplemental Appropriation Ordinance will be forthcoming to supplement the 2024 adopted budget to absorb this grant cost.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT# |
|
AMOUNT |
|
|
AMENDMENT |
|
CONTRACT# |
|
AMOUNT |
|
Contract Period
|
ORIGINAL |
START |
|
END |
|
|
AMENDMENT |
START |
|
END |
|
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.