Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the County Executive to sign Change Order Number CO-07 to Bid PW23-003SB with Hi-Mark Construction Inc. for the Courtroom 3D Tenant Improvements.
body
DEPARTMENT: Facilities and Fleet
ORIGINATOR: Anna Morton
EXECUTIVE RECOMMENDATION: Click or tap here to enter text.
PURPOSE: To obtain Executive approval of PW-23-003SB Change Order 07
BACKGROUND: The County and Hi-Mark Construction Inc. entered into an agreement on April 7, 2023, for the Courtroom 3D Tenant Improvements project. Superior Court requested additional AV equipment for this Courtroom. Change Order CO-07 covers items typically associated with changes in construction projects. The changes include items for unexpected hidden conditions (uneven floor, CMU protruding wall), clarifications of design elements that became apparent to the end users after some construction was in place (faucets to better fit the sinks, additional cable trays), and design revisions requested by the end user (reworking of the 3C Chambers).
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
311 527 18001 6000
$16,765.86 + tax
TOTAL
$16,765.86 + tax
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
TOTAL
DEPARTMENT FISCAL IMPACT NOTES: There is sufficient budget authority-no increase requested.
CONTRACT INFORMATION:
ORIGINAL
CONTRACT#
PW-23-003SB
AMOUNT
$709,900.00
Change Order
01
CONTRACT#
Same
AMOUNT
$58,035.44
Change Order
02
CONTRACT#
Same
AMOUNT
$3,169.40
Change Order
03
CONTRACT#
Same
AMOUNT
$65,273.08
Change Order
04
CONTRACT#
Same
AMOUNT
$300,096.75
Change Order
05
CONTRACT#
Same
AMOUNT
$10,944.94
Change Order
06
CONTRACT #
Same
AMOUNT
$26,323.95
Change Order
07
CONTRACT #
Same
AMOUNT
$16,765.86
TOTAL $1,190,509.42
Contract Period
ORIGINAL
START
4/7/2023
END
Final Project Acceptance Date
AMENDMENT
START
Upon Execution
END
Same
OTHER D...
Click here for full text