Legislation Details

File #: 2026-2466    Version: 1
Type: Motion Status: Regular Agenda
File created: 9/23/2026 In control: Committee of the Whole
On agenda: 10/14/2026 Final action:
Title: Motion 26-400, approving Change Order No. 9 to the Arlington Operations Center Agreement with Cornerstone General Contractors
Attachments: 1. Proposed Motion 26-400, 2. Staff Report, 3. Change Order #9, 4. Progressive Design Build Contract Executed, 5. Amendment 1 Executed, 6. Amendment 2 Executed, 7. Amendment 3 Executed, 8. Amendment 4 Executed, 9. Amendment 5 Executed, 10. Certificate of Insurance, 11. Change Order #1 Executed, 12. Change Order #2 Executed, 13. Change Order #3 Executed, 14. Change Order #4 Executed, 15. Change Order #5 Executed, 16. Change Order #6 Executed, 17. Change Order #7 Executed, 18. Change Order #8 Executed, 19. Motion Assignment Slip


Executive/Council Action Form (ECAF)


ITEM TITLE:
Title
Motion 26-400, approving Change Order No. 9 to the Arlington Operations Center Agreement with Cornerstone General Contractors
body

DEPARTMENT: Public Works

ORIGINATOR: Kelli Kunz

EXECUTIVE RECOMMENDATION: Approved (Tom Teigen 10/1/2026)

PURPOSE: Approval of Change Order #9 to authorize payment to the Contractor, Cornerstone General Construction for added work associated Redesign of the EV Charging System

BACKGROUND: The Department of Public Works determined the need to construct a new road operations center and emergency response facility at the County’s Arlington Operations site located in Arlington, WA. • Through a Request for Qualifications and a subsequent Request for Proposal Public Works solicited the services of a Design Build Contractor or Consultant to assist the County with this project. Cornerstone General Contractors responded to RFQ-23-001SB and RFP-23-004SB and was selected through established Federal State and County policies and practices. • Snohomish County and Cornerstone General Construction entered into agreement on December 13, 2023, for the design and construction of the Arlington Operations Center under Progressive Design Build Agreement PDB01-23. • To date, PW has executed five amendments to the original agreement which include Validation (Motion No. 24-097), Design (Motion No. 24-317), Granite Falls Stating Site Construction (Motion No. 25-302) and Arlington Operations primary site construction (Motion No. 25-320). • This project was not bid but selected through an RFQ/RFP process and therefore requires Council approval for any contract amendments above $100,000 or 20% of the contract value, whichever is less. • To date there have been five amendments and six change orders approved by Council, and two change orders and one amendment approved by the PW Director. • An additional change order is needed above the PW Director’s authority and requires Council consideration: Cha...

Click here for full text