Legislation Details

File #: 2026-1066    Version: 1
Type: Executive Status: Executive Approved
File created: 4/22/2026 In control: Executive
On agenda: Final action: 4/27/2026
Title: Authorizing the Executive to sign Change Order CO-39 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
Attachments: 1. PW-24-027SB Certificate of Insurance, 2. PW-24-027SB Agreement, 3. PW24-027SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 05, 10. PW-24-027SB Change Order 06, 11. PW-24-027SB Change Order 07, 12. PW-24-027SB Change Order 08, 13. PW-24-027SB Change Order 09, 14. PW-24-027SB Change Order 10, 15. PW-24-027SB Change Order 11, 16. PW-24-027SB Change Order 12, 17. PW-24-027SB Change Order 13, 18. PW-24-027SB Change Order 14, 19. PW-24-027SB Change Order 15, 20. PW-24-027SB Change Order 16, 21. PW-24-027SB Change Order 17, 22. PW-24-027SB Change Order 18, 23. PW-24-027SB Change Order 19, 24. PW-24-027SB Change Order 20, 25. PW-24-027SB Change Order 21, 26. PW-24-027SB Change Order 22, 27. PW-24-027SB Change Order 23, 28. PW-24-027SB Change Order 24, 29. PW-24-027SB Change Order 25, 30. PW-24-027SB Change Order 26, 31. PW-24-027SB Change Order 27, 32. PW-24-027SB Change Order 28, 33. PW-24-027SB Change Order 29, 34. PW-24-027SB Change Order 30, 35. PW-24-027SB Change Order 31, 36. PW-24-027SB Change Order 32, 37. PW-24-027SB Change Order 33, 38. PW-24-027SB Change Order 34, 39. PW-24-027SB Change Order 35, 40. PW-24-027SB Change Order 36, 41. PW-24-027SB Change Order 37, 42. PW-24-027SB Change Order 38, 43. PW-24-027SB Change Order 39 - SIGNED
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.


Executive/Council Action Form (ECAF)


ITEM TITLE:
Title
Authorizing the Executive to sign Change Order CO-39 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
body
DEPARTMENT: Facilities and Fleet Management

ORIGINATOR: Lance Meinhold

EXECUTIVE RECOMMENDATION: Approved

PURPOSE: To obtain Executive approval of Change Order 39 to Marpac Construction.

BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The contractor discovered the existing wiring for the back building could not be relocated the few feet required to accommodate the new electrical gear upon starting demolition of the existing electrical gear. The existing gear was atypically set up to feed from the top left, near the center of the building. Electrical gear is typically installed to feed at the side closest to the exterior of the building, in this case the right side. The entire project team explored several alternatives. Field modifying the gear has the least impact to the schedule and costs. The change order proposal has been negotiated down $1,288. The electrical requirements for the electrical dryer were incorrect on the bid documents. The engineer referenced the dryer for the Edmonds locations, which is primarily gas, rather than the higher electrical load required for Everett. The revision was issued with other changes during construction. The contractor initially missed the feed to the electrical dryer with those revisions. The revision was identified recently in the field. The cost of the change has been negotiated down by $8,565.

FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
002 5123116201
$47,072.00














TOTAL
$47,072.00




REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
















TOTAL




DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to e...