Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the Executive to sign of Change Order CO-25 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
body
DEPARTMENT: Facilities and Fleet Management
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 25 to Marpac Construction.
BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The Salvation Army requested additional CCTV and WAP locations to ensure proper coverage for security purposes. The wall behind the former food prep areas in the kitchen were discovered to be covered in oil and grime when the cabinets were removed. Replacement of the drywall was deemed safer and more simple than attempting to clean the areas.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
002 5123116201
$37,182.00
TOTAL
$37,182.00
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
TOTAL
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL
CONTRACT #
PW 24-027SB
AMOUNT
$4,040,000.00
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$12,354.58
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$71,578.14
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$7,040.92
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$16,843.95
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$200,329.05
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$143,596.21
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$106,047.50
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$53,786.28
AMENDMENT|10 10|CONTRACT #
PW 24-027SB
AMOUNT
$123,892.39
AMENDMENT
10
CONTRACT #
PW 24-027SB
AMOUNT
$116,751.01
AMENDMENT
11
CONTRACT #
PW 24-027SB
AMOUNT
$126,919.65
AMENDMENT
12
CONTRACT #
PW 24-027SB
AMOUNT
$63,703.30
AMENDMEN...