Legislation Details

File #: 2025-3283    Version: 1
Type: Executive Status: Executive Approved
File created: 10/6/2025 In control: Executive
On agenda: Final action:
Title: Authorizing the Executive to sign of Change Order CO-22 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
Attachments: 1. PW-24-027SB Certificate of Insurance, 2. PW-24-027SB Agreement, 3. PW24-027SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 05, 10. PW-24-027SB Change Order 06, 11. PW-24-027SB Change Order 07, 12. PW-24-027SB Change Order 08, 13. PW-24-027SB Change Order 09, 14. PW-24-027SB Change Order 10, 15. PW-24-027SB Change Order 11, 16. PW-24-027SB Change Order 12, 17. PW-24-027SB Change Order 13, 18. PW-24-027SB Change Order 14, 19. PW-24-027SB Change Order 15, 20. PW-24-027SB Change Order 16, 21. PW-24-027SB Change Order 17, 22. PW-24-027SB Change Order 18, 23. PW-24-027SB Change Order 19, 24. PW-24-027SB Change Order 20, 25. PW-24-027SB Change Order 21, 26. PW-24-027SB Change Order 22 - Proposed, 27. PW-24-027SB Change Order 22 - EXEC SIGNED
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.


Executive/Council Action Form (ECAF)


ITEM TITLE:
Title
Authorizing the Executive to sign of Change Order CO-22 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
body
DEPARTMENT: Facilities and Fleet Management

ORIGINATOR: Lance Meinhold

EXECUTIVE RECOMMENDATION: Approved

PURPOSE: To obtain Executive approval of Change Order 22 to Marpac Construction.

BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. The existing electrical feeder wires were of the precise length to reach their terminations within the existing electrical panels. The new panels are physically bigger. The wires will reach into the panels but will not reach the new termination points. Splicing the wires within the panel box is allowed by code. The work will be difficult to preform within the limited space of the panel's box. The electricians are confident they can splice the wiring correctly but will need to take care to make each splice at the correct location to fit the splices within the box. The alternative is to run new wiring for the full length of the existing runs. The change order takes advantage of reusing the pre-run existing wiring.

FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
002 5123116201
$11,595.00














TOTAL
$11,595.00




REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
















TOTAL




DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.

CONTRACT INFORMATION:
ORIGINAL

CONTRACT #
PW 24-027SB
AMOUNT
$4,040,000.00
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$12,354.58
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$71,578.14
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$7,040.92
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$16,843.95
AMENDMENT|1010|CONTRACT #
PW 24-027SB
AMOUNT
$200,329.05
AMENDMENT|1010|CONTRACT...