Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the County Executive to sign Change Order CO-08 to Bid PW-24-028SB with Lincoln Construction, Inc. for the Construction at the New Start Center of Edmonds.
body
DEPARTMENT: Facilities and Fleet
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 08 to Lincoln Construction, Inc.
BACKGROUND: The County and Lincoln Construction Inc. (LCi) entered into an agreement on December 19th, 2024, for the construction phase of the New Start Center of Edmonds. Changes have been made due to the city plan review comments after the project was bid. Additional demolition will be required based on revisions made during the city's plan review period. Additional flooring, site demolition, and restroom accessories are required. A new wall unit heater will be installed to replace the unit that was removed during the moisture remediation process that occurred after the bid process.
FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
124 509 044 6201
$70,783.00
TOTAL
$70,783.00
REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
TOTAL
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
ORIGINAL
CONTRACT#
PW24-028SB
AMOUNT
$2,474,000.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$547,000.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$128,884.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$-46,570.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$13,099.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$163,150.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$32,132.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$160,006.00
AMENDMENT|1010|CONTRACT#
PW24-028SB
AMOUNT
$70,783.00
TOTAL
$3,542,484.00
Contract Period
ORIGINAL
START
12/19/2024
END
Final Project Acceptance Date
AMENDMENT
START
Upon Execution
END
Same - Unchanged
...
Click here for full text