Legislation Details

File #: 2025-2077    Version: 1
Type: Executive Status: Executive Approved
File created: 6/24/2025 In control: Executive
On agenda: Final action:
Title: Amendment No. 8 to the Professional Services Agreement for Whitehorse Trail Design and Improvements (RFQ 13-21SB)
Attachments: 1. 13-21SB_WHT_Amendment 1_Time Extension SS Signed, 2. 13-21SB_WHT_Amendment 2_Time Extension Signed, 3. 13-21SB_WHT_Amendment 3_Time Extension (002) Signed, 4. 13-21SB_WHT_Amendment 4_Time Only Extension SS signed, 5. 13-21SB_WHT_Amendment 5_Time Only Extension Signed, 6. 13-21SB_WHT_Amendment 8_Time Only Extension, 7. 2024-2496_DCNR_Contract with BCE_Amendment 7_signed, 8. 2025 Auto Liability COI, 9. 2025 Commercial COI, 10. 2025-2026 Workers Comp & Professional COI, 11. BCE Consulting Amendment 6_2024_signed by L.Harper, 12. Motion 22-404, 13. WHT_Pro-Forma_BCE_Final_Signed, 14. 13-21SB_WHT_Amendment 8_Time Only Extension Signed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.


Executive/Council Action Form (ECAF)


ITEM TITLE:
Title
Amendment No. 8 to the Professional Services Agreement for Whitehorse Trail Design and Improvements (RFQ 13-21SB)
body
DEPARTMENT: DCNR/Parks

ORIGINATOR: Emily Griffith

EXECUTIVE RECOMMENDATION: Approved

PURPOSE: Approval for Professional Services Agreement Amendment No. 8 with Bratslavsky Consulting Engineers, Inc. for additional time to complete current phase of design services and permitting support.

BACKGROUND: A consultant contract for professional services for Whitehorse Trail Design and Improvements was executed with Bratslavsky Consulting Engineers, Inc. on September 29, 2022 to provide design services for the Whitehorse Trail. The initial contract was for site analysis and conceptual design, followed by five subsequent time-only amendments to allow the County additional time to review the schematic design options and to progress in easement negotiations and to determine design direction. Amendment No. 7 included services for the next phase of design and engineering and permitting for the project. This Amendment, No. 8, is a time-only extension to allow for additional time to complete permitting and 100% design and engineering.

FISCAL IMPLICATIONS:
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU
CURRENT YR
2ND YR
1ST 6 YRS
















TOTAL





REVENUE: FUND, AGY, ORG, REV, SOURCE
CURRENT YR
2ND YR
1ST 6 YRS
















TOTAL




DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.

CONTRACT INFORMATION:
ORIGINAL
X
CONTRACT#
RFQ-13-21SB
AMOUNT
$202,793.74
AMENDMENT|1010|CONTRACT#

AMOUNT
$0
|1010|


$0
|1010|


$0
|1010|


$0
|1010|


$0
|1010|


$397,748.82
|1010|


$9,579.10
|1010|


$0

Contract Period
ORIGINAL
START
9/29/2022
END
3/31/2023
AMENDMENT
START

END
5/31/2023

START

END
7/31/2023

START

END
9/30/2023

START

END
11/30/2023

START

END
1/31/2024

START

END
6/30/2025

START

END
6/30/2025

START

END
2/28/2026

OTHER DEPARTMENTAL REVIEW/COMMENTS: Cl...

Click here for full text