Legislation Details
|
File #:
|
2025-2026
Version:
1
|
|
|
|
Type:
|
Executive
|
Status:
|
Executive Approved
|
|
File created:
|
6/20/2025
|
In control:
|
Executive
|
|
Title:
|
Authorizing the Executive to sign Change Order CO-06 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
|
|
Attachments:
|
1. PW-24-027SB Certificate of Insurance, 2. PW-24-027SB Agreement, 3. PW24-027SB Tracking Log, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 05, 10. PW-24-027SB Change Order 06, 11. PW-24-027SB Change Order 06signed, 12. PW-24-027SB Change Order 05signed
|
Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Authorizing the Executive to sign Change Order CO-06 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
body
DEPARTMENT: Facilities and Fleet Management
ORIGINATOR: Lance Meinhold
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: To obtain Executive approval of Change Order 06 to Marpac Construction.
BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. Several changes to the documents occurred between the Bid Set and the Permit set. Abate additional asbestos containing materials only as required to complete the remodel. This abatement work will be completed on a Time & Materials basis and is intended to cover the work at the resident rooms in the back building.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
124 509 044 66 6201 |
$143,596.21 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
$143,596.21 |
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT # |
PW 24-027SB |
AMOUNT |
$4,040,000.00 |
|
AMENDMENT |
1 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$12,254.58 |
|
AMENDMENT |
2 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$71,578.14 |
|
AMENDMENT |
3 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$7,040.92 |
|
AMENDMENT |
4 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$16,843.95 |
|
AMENDMENT |
5 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$188,177.66 |
|
AMENDMENT |
6 |
CONTRACT # |
PW 24-027SB |
AMOUNT |
$143,596.21 |
|
|
|
|
|
TOTAL |
$4,479,491.46 |
Contract Period
|
ORIGINAL |
START |
12/18/2024 |
END |
Final Project Acceptance Date |
|
AMENDMENT |
START |
Upon Execution |
END |
Same - Unchanged |
OTHER DEPARTMENTAL REVIEW/COMMENTS: Click or tap here to enter text.
|