Legislation Details

File #: 2025-1905    Version: 1
Type: Executive Status: Executive Approved
File created: 6/9/2025 In control: Executive
On agenda: Final action:
Title: Authorizing the Executive to sign of Change Order CO-04 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.
Attachments: 1. PW-24-027SB Certificate of Insurance, 2. PW24-027SB Tracking Log, 3. PW-24-027SB Agreement, 4. Motion 24-417, Amended, 5. PW-24-027SB Change Order 01, 6. PW-24-027SB Change Order 02, 7. PW-24-027SB Change Order 03, 8. PW-24-027SB Change Order 04, 9. PW-24-027SB Change Order 04 EXEC SIGNED
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

Executive/Council Action Form (ECAF)

 

 

ITEM TITLE:

Title

Authorizing the Executive to sign of Change Order CO-04 to Bid PW-24-027SB for the Construction at the New Start Center of Everett with Marpac Construction LLC.

body

DEPARTMENT:  Facilities and Fleet Management

 

ORIGINATOR:  Lance Meinhold

 

EXECUTIVE RECOMMENDATION:  Click or tap here to enter text.

 

PURPOSE: To obtain Executive approval of Change Order 04 to Marpac Construction.

 

BACKGROUND: The County and Marpac Construction entered into an agreement on December 18th, 2024, for the construction phase of the New Start Center of Everett. 31 toilet flanges have been discovered as broken and require repair. The building does not have any valves on the water supply line to isolate areas. The contractor has suggested adding isolation valves to aid in future maintenance issues. Door hardware has been ordered, unfortunately, there were tariffs in place as the time of ordering. The tariffs changed the pricing on approximately 5% of the door hardware - manufactured in Mexico. A PTAC unit is being relocated due to a fire-resistant rated wall issue.

 

FISCAL IMPLICATIONS:

EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU

CURRENT YR

2ND YR

1ST 6 YRS

124 509 044 66 6201

$16,843.95

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

$16,843.95

 

 

 

 

REVENUE: FUND, AGY, ORG, REV, SOURCE

CURRENT YR

2ND YR

1ST 6 YRS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOTAL

 

 

 

 

DEPARTMENT FISCAL IMPACT NOTES:  Click or tap here to enter text.

 

CONTRACT INFORMATION:

ORIGINAL

 

CONTRACT #

PW 24-027SB

AMOUNT

$4,040,000.00

AMENDMENT

1

CONTRACT #

PW 24-027SB

AMOUNT

$12,254.58

AMENDMENT

2

CONTRACT #

PW 24-027SB

AMOUNT

$71,578.14

AMENDMENT

3

CONTRACT #

PW 24-027SB

AMOUNT

$7,040.92

AMENDMENT

4

CONTRACT #

PW 24-027SB

AMOUNT

$16,843.95

 

 

 

 

TOTAL

$4,147,717.59

 

Contract Period

ORIGINAL

START

12/18/2024

END

Final Project Acceptance Date

AMENDMENT

START

Upon Execution

END

Same - Unchanged

 

OTHER DEPARTMENTAL REVIEW/COMMENTS:  Click or tap here to enter text.