Executive/Council Action Form (ECAF)
ITEM TITLE:
Title
Approve amendment No. 1 to the agreement between the Washington State Association of Counties and Snohomish County for the energy audits of Tier 1 and Tier 2 Buildings.
body
DEPARTMENT: Facilities and Fleet
ORIGINATOR: Alex Pidduck
EXECUTIVE RECOMMENDATION: Approved
PURPOSE: Obtain executive approval of Amendment No. 1 relating to the performance period.
BACKGROUND: In 2024, the Washington Association of Counties (WSAC) introduced the Energy Audit Grant Program, which provides reimbursable payments for energy audits and other work completed between July 1, 2024 and June 30, 2025. In February 2025, the WSAC Energy Audit Grant Agreement was executed with an end date of June 30, 2025. An extension opportunity for the performance period was recently made available and requested by Facilities and Fleet.
FISCAL IMPLICATIONS:
|
EXPEND: FUND, AGY, ORG, ACTY, OBJ, AU |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
|
REVENUE: FUND, AGY, ORG, REV, SOURCE |
CURRENT YR |
2ND YR |
1ST 6 YRS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
DEPARTMENT FISCAL IMPACT NOTES: Click or tap here to enter text.
CONTRACT INFORMATION:
|
ORIGINAL |
|
CONTRACT# |
|
AMOUNT |
|
|
AMENDMENT |
1 |
CONTRACT# |
WSAC Energy Audit Grant |
AMOUNT |
0.00 |
Contract Period
|
ORIGINAL |
START |
July 1, 2024 |
END |
June 30, 2025 |
|
AMENDMENT |
START |
July 1, 2024 |
END |
October 31, 2025 |